Release process » History » Revision 7
Revision 5 (Tomas Murphy, 07/19/2026 09:46 AM) → Revision 7/8 (Charlotte Lambert, 08/11/2026 09:46 AM)
h1. Release process
h2. Schedule
Planned releases are listed in the *Roadmap* tab. Hotfixes can go out any weekday before 16:00.
h2. Steps
# Freeze the scope: only fixes after the release candidate.
# QA runs the regression suite on the release candidate.
# DevOps deploys with the blue-green pipeline.
# Monitor error rate and latency for 30 minutes.
# Publish the release notes and close the version.
h2. Rollback
Switch the traffic back to the previous environment; database migrations are written to be backward compatible for one release.
* Update 2026-06-17: Pushed a fix, please check on staging.
* Update 2026-07-19: Pushed a fix, please check on staging.
* Update 2026-08-11: Found one more case, added a test for it.