Release process

Schedule

Planned releases are listed in the Roadmap tab. Hotfixes can go out any weekday before 16:00.

Steps

  1. Freeze the scope: only fixes after the release candidate.
  2. QA runs the regression suite on the release candidate.
  3. DevOps deploys with the blue-green pipeline.
  4. Monitor error rate and latency for 30 minutes.
  5. Publish the release notes and close the version.

Rollback

Switch the traffic back to the previous environment; database migrations are written to be backward compatible for one release.

  • Update 2026-06-05: Pushed a fix, please check on staging.
  • Update 2026-06-08: Moved to the next sprint because of higher priority hotfixes.