Project

General

Profile

Resource planning

Filters

Zoom in Zoom out

months from Apply Clear

 
Feb 02 - Feb 04
Feb 05 - Feb 11
Feb 12 - Feb 18
Feb 19 - Feb 25
Feb 26 - Mar 03
Mar 04 - Mar 10
Mar 11 - Mar 17
Mar 18 - Mar 24
Mar 25 - Mar 31
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
 1h
Underload: 1h

Total scheduled: 7h
Total: 8h
 Setup CI server
Dates: Mon, 01 Apr - Wed, 10 Apr
Scheduled: 7 h/d for 8 days (2 days off)
Total: 56 hours for 8 days (2 days off)

Issue: Task #584: Setup CI server
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 04/04/2024
Due date:
Assignee: Pong Steven
Author: Smith Paul