Project

General

Profile

Resource planning

Filters

Zoom in Zoom out

months from Apply Clear

 
Dec 02 - Dec 03
Dec 04 - Dec 10
Dec 11 - Dec 17
Dec 18 - Dec 24
Dec 25 - Dec 31
Jan 01 - Jan 07
Jan 08 - Jan 14
Jan 15 - Jan 21
Jan 22 - Jan 28
Jan 29 - Feb 01
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
 1h
Underload: 1h

Total scheduled: 7h
Total: 8h
 Setup CI server
Dates: Thu, 01 Feb - Sat, 10 Feb
Scheduled: 7 h/d for 7 days (3 days off)
Total: 49 hours for 7 days (3 days off)

Issue: Task #584: Setup CI server
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 02/04/2024
Due date:
Assignee: Pong Steven
Author: Smith Paul