Meeting notes

Sprint review

  • Demo of the completed tasks to the stakeholders.
  • Feedback is logged as new tasks in the backlog.

Retrospective

  • Keep: short daily syncs, review turnaround under one day.
  • Improve: estimates for integration work, test data setup.
  • Try: pair sessions for the most complex tasks.
  • Update 2026-06-16: Needs clarification from the client, asked in the shared channel.
  • Update 2026-06-21: Ready for review.
  • Update 2026-08-15: Ready for review.