Roadmap » History » Revision 9

Revision 7 (Zoe Schmidt, 07/08/2026 07:42 PM) → Revision 9/10 (Yuki Owens, 08/07/2026 07:42 PM)

h1. Roadmap 

 h2. Next release 

 The scope of the next release is the list of tasks assigned to the open version with the nearest due date. 

 h2. Later 

 * Improve onboarding and first-run experience 
 * Reporting and exports 
 * Integrations requested by customers 
 * Performance and cost reduction 


 * Update 2026-05-18: Needs clarification from the client, asked in the shared channel. 

 * Update 2026-05-23: Started working on it, will post an update after the first run. 

 * Update 2026-07-08: Reproduced the problem; the cause is in the data migration. 

 * Update 2026-08-07: Ready for review.