Actions
Release process » History » Revision 7
« Previous |
Revision 7/8
(diff)
Lucas Xu, 07/05/2026 03:29 PM
Minor update
Release process¶
Schedule¶
Planned releases are listed in the Roadmap tab. Hotfixes can go out any weekday before 16:00.
Steps¶
- Freeze the scope: only fixes after the release candidate.
- QA runs the regression suite on the release candidate.
- DevOps deploys with the blue-green pipeline.
- Monitor error rate and latency for 30 minutes.
- Publish the release notes and close the version.
Rollback¶
Switch the traffic back to the previous environment; database migrations are written to be backward compatible for one release.
- Update 2026-06-06: Pushed a fix, please check on staging.
- Update 2026-07-20: Started working on it, will post an update after the first run.
- Update 2026-07-05: Tested locally and on staging, all green.
Updated by Lucas Xu 4 months ago · 4 revisions