Project

General

Profile

Meeting notes » History » Version 9

Liam Larsen, 08/08/2026 07:42 PM
Minor update

1 1 Daniel Haddad
h1. Meeting notes
2
3
h2. Sprint review
4
5
* Demo of the completed tasks to the stakeholders.
6
* Feedback is logged as new tasks in the backlog.
7
8
h2. Retrospective
9
10
* Keep: short daily syncs, review turnaround under one day.
11
* Improve: estimates for integration work, test data setup.
12
* Try: pair sessions for the most complex tasks.
13 3 Zoe Zimmerman
14
15
* Update 2026-06-04: Updated the description with the final acceptance criteria.
16 5 Theodore Carter
17
* Update 2026-07-07: Started working on it, will post an update after the first run.
18 7 Tomas Murphy
19
* Update 2026-07-29: Moved to the next sprint because of higher priority hotfixes.
20 9 Liam Larsen
21
* Update 2026-08-08: Merged to main, will be included in the next release.