User story #578: Edit Project with many lines. How will it look like on the board
User story #579: Assign Task to Area
User story #587: Sortable board cards
Task #584: Setup CI server
User story #583: Print Tasks
 
Aug 18 - Aug 23
Aug 24 - Aug 30
Aug 31 - Sep 06
Sep 07 - Sep 13
Sep 14 - Sep 20
Sep 21 - Sep 27
Sep 28 - Oct 04
Oct 05 - Oct 11
Oct 12 - Oct 17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
 1h
Underload: 1 h

Total scheduled: 7 h
Total: 8 h
 -1.5h
Overload: 1.5 h

Total scheduled: 9.5 h
Total: 8 h
 1.5h
Underload: 1.5 h

Total scheduled: 6.5 h
Total: 8 h
 F
Load: Full load

Total scheduled: 8 h
Total: 8 h
 -5.5h
Overload: 5.5 h

Total scheduled: 13.5 h
Total: 8 h
 -4h
Overload: 4 h

Total scheduled: 12 h
Total: 8 h
 -9h
Overload: 9 h

Total scheduled: 17 h
Total: 8 h
 
 
Sprint #3
 
Sprint #1
 Edit Project with many lines. How will it look like on the board
Dates: Sat, 03 Oct - Sun, 18 Oct
Scheduled: 4 h/d for 10 days (6 days off)
Total: 40 hours for 10 days (6 days off)

Issue: User story #578: Edit Project with many lines. How will it look like on the board
Project: Redmine Agile plugin demo
Status: In Progress
Start date: 10/06/2020
Due date:
Assignee: Wozniak Stephen
 Assign Task to Area
Dates: Mon, 05 Oct - Wed, 07 Oct
Scheduled: 3 h/d for 3 days
Total: 9 hours for 3 days

Issue: User story #579: Assign Task to Area
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 10/01/2020
Due date:
Assignee: Pong Steven
 Sortable board cards
Dates: Tue, 06 Oct - Mon, 12 Oct
Scheduled: 2.5 h/d for 5 days (2 days off)
Total: 12.5 hours for 5 days (2 days off)

Issue: User story #587: Sortable board cards
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 10/03/2020
Due date:
Assignee: Kutcher Ashton
 Setup CI server
Dates: Sat, 10 Oct - Tue, 13 Oct
Scheduled: 1.5 h/d for 2 days (2 days off)
Total: 3 hours for 2 days (2 days off)

Issue: Task #584: Setup CI server
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 10/04/2020
Due date:
Assignee: Pong Steven
 Print Tasks
Dates: Fri, 16 Oct - Mon, 19 Oct
Scheduled: 5 h/d for 2 days (2 days off)
Total: 10 hours for 2 days (2 days off)

Issue: User story #583: Print Tasks
Project: Redmine Agile plugin demo
Status: New
Start date: 10/04/2020
Due date:
Assignee:
 F
Load: Full load

Total scheduled: 6 h
Total: 6 h
 F
Load: Full load

Total scheduled: 6 h
Total: 6 h
 1h
Underload: 1 h

Total scheduled: 5 h
Total: 6 h
 
 
Sprint #3
 
Sprint #1
 Assign Task to Area
Dates: Wed, 07 Oct - Mon, 19 Oct
Scheduled: 5 h/d for 9 days (4 days off)
Total: 45 hours for 9 days (4 days off)

Issue: User story #579: Assign Task to Area
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 10/01/2020
Due date:
Assignee: Pong Steven
 1h
Underload: 1 h

Total scheduled: 7 h
Total: 8 h
 1h
Underload: 1 h

Total scheduled: 7 h
Total: 8 h
 
 
Sprint #3
 
Sprint #1
 Setup CI server
Dates: Thu, 01 Oct - Sat, 10 Oct
Scheduled: 7 h/d for 7 days (3 days off)
Total: 49 hours for 7 days (3 days off)

Issue: Task #584: Setup CI server
Project: Redmine Agile plugin demo
Status: Resolved
Start date: 10/04/2020
Due date:
Assignee: Pong Steven
« Previous Next »